Multipurpose Building
![]()
May 30
![]()
May 23
![]()
May 23
![]()
May 16
![]()
May 16
![]()
May 16
![]()
May 9
![]()
May 9
![]()
May 2
![]()
May 2
![]()
April 25
![]()
April 25
![]()
April 25
![]()
April 11
![]()
April 11
![]()
March 21
![]()
March 21
![]()
March 21
![]()
March 14
![]()
March 7
![]()
March 7
![]()
February 28
![]()
February 17
![]()
February 10
![]()
February 10
![]()
February 3
![]()
February 3
![]()
January 27
![]()
January 27
![]()
January 24
![]()
January 20
![]()
January 17
![]()
January 17
![]()
January 17
![]()
January 13
![]()
January 6, 2025
![]()
January 6, 2025
![]()
January 6, 2025
![]()
January 3, 2025
![]()
January 3, 2025
![]()
December 30, 2024
![]()
December 20, 2025
![]()
December 13, 2024
![]()
December 6, 2024
![]()
November 22, 2024
![]()
November 22, 2024
![]()
November 22, 2024
![]()
November 11, 2024
![]()
November 11, 2024
Construction (November 2024-present)
- installation of fencing and site set-up
- staking out utilities and building layout
- working with subcontractors on documents and submittals for materials
- issuance of building permit
- demo and stripping of the topsoil
- stockpiling topsoil
- proofrolling and getting the pad ready
- preparation of building pad
- installing silt fence
- laying additional rock to protect the building pad and the pathway to the building pad
- delivery of pre-engineered building
- digging and pouring concrete footers for building
- forming and pouring foundation walls
- setting anchor bolts in place
- waterproofing and insulating the footers
- erecting the building
- completing the structure of the building
- completing the siding
- backfilling the perimeter of the foundation wall
- hanging main steel
- hanging siding panels
- cleaning up ruts and soft soil
- completing electrical and plumbing work under the concrete slab
- installing banding for the roof
- beginning roof insulation
- finishing the roofing and ridge cap
- starting gutters and finishing trim
- prepping and pouring concrete for the slab on grade
- finishing gutters
- cleaning site ruts and tracks
- staking storm and sanitary pit
- finishing the building trim and cleaning the building panels
- beginning framing with metal studes for walls
- completing storm drain
- completing electrical and plumbing rough-in
- beginning to sheath main room
- hanging drywall, mudding, and finishing
- finishing electrical install
- completing insulation
- topping off drywall
- spreading topsoil and seed
- installing exterior frames and doors
- painting steel and ceiling structure
- finalizing the sanitary pit
- distributing top soil
- applying final paint
- finishing exterior doors
- completing electrical finishes
- installing sanitary pumps
- finishing electrical, mechanical, and plumbing
- installing lockers
- installing wall bases
- continued inspections by county and testing agencies
Pre-Construction (June-October 2024)
- site survey for grade, utilities, drainage, etc.
- soil borings to determine soil materials, moisture content, and bearing capacity
- electrical engineer on site
- sanitary study
- review of floor plans and specifications
- technology/mechanical coordination
- final review of drawings
- issue of stamped permit
- Greene County Public Health permit approved
- Greene County building permit issued