Construction (November 2024-present)
- installation of fencing and site set-up
- staking out utilities and building layout
- working with subcontractors on documents and submittals for materials
- issuance of building permit
- demo and stripping of the topsoil
- stockpiling topsoil
- proofrolling and getting the pad ready
- preparation of building pad
- installing silt fence
- laying additional rock to protect the building pad and the pathway to the building pad
- delivery of pre-engineered building
- digging and pouring concrete footers for building
- inspection by county and testing agency
Pre-Construction (June-October 2024)
- site survey for grade, utilities, drainage, etc.
- soil borings to determine soil materials, moisture content, and bearing capacity
- electrical engineer on site
- sanitary study
- review of floor plans and specifications
- technology/mechanical coordination
- final review of drawings
- issue of stamped permit
- Greene County Public Health permit approved
- Greene County building permit issued